Bury Interchange Metrolink car park closed until Friday as improvement works begin

100 free spaces at Q-Park Knowsley Place while a construction compound is set up; the car park reopens on 28 November with fewer spaces
Bury Interchange Metrolink car park closed until Friday as improvement works begin

The Metrolink park and ride car park at Bury Interchange is closed until Friday 27 November while a construction compound is set up for the first phase of the interchange redevelopment, Transport for Greater Manchester (TfGM) says.

 

The closure started on Monday 23 November. The car park is due to reopen on Saturday 28 November, but with fewer spaces while construction continues. The changes were first reported by the Manchester Evening News.

 

Where to park this week

 

According to TfGM, during the closure:

 

  • accessible parking bays at the Metrolink car park stay open;
  • 100 free spaces are available at Q-Park Knowsley Place, first come, first served. Drivers must collect a ticket token from the Bury Interchange Metrolink park and ride site first, before entering Q-Park;
  • other park and ride spaces are available at Radcliffe (M26 2SZ) and Whitefield (M45 8QH) tram stops.

 

TfGM's infrastructure delivery director Chris Barnes said in a statement reported by the Manchester Evening News that once the car park reopens "there will be slightly fewer spaces available during construction".

 

What is being built

 

TfGM says phase one runs from November 2026 to early 2028 and received planning permission in July 2025. It includes:

 

  • a new footbridge over the tram lines linking to Union Square, with step-free access to Pyramid Park;
  • new stairs and a lift down to the platforms;
  • refurbished platforms with new canopies, resurfacing, better passenger information, lighting, signage and CCTV;
  • temporary stepped access at the north end of the eastern platform, due to open in late 2027 or early 2028.

 

Phase two, from early 2028 to 2030 and subject to approvals, would replace the interchange with a fully enclosed building with a waiting area, accessible toilets including a Changing Places facility, a cycle hub, redesigned bus areas and proposed rental apartments, TfGM says. The Manchester Evening News reported that phase two is an upgrade of around £80m. TfGM says a public consultation on phase two is scheduled to launch in winter 2026.

 

Trams will continue to run into Bury for most of the programme, but TfGM says there will be times when they cannot. Passengers will be told in advance, including about any replacement buses. The work is being delivered with Bury Council and the Greater Manchester Combined Authority, and is funded through the government's City Region Sustainable Transport Settlement.

 

Sources: Transport for Greater Manchester (Bury Interchange project page, accessed 24 November 2026); TfGM travel alerts (Bury tram stop park and ride closure, updated 19 November 2026); Manchester Evening News (19 November 2026). Photo: illustrative stock image. This article was produced with the help of AI tools and checked by an editor against the sources above.